News Flash

Home Spotlights

Posted on: July 2, 2021

Road Resurfacing Continues

DSC03142 (3)

Nearly 8 miles of roads will be resurfaced this year. The updated schedule is:

Tuesday, August 24          

            Gillin Road

            Mercer Hill Road

            Jefron Drive

 

Wednesday, August 25

            Gordon Road

            Paddock Road

            Start Detweiler Lane/Graystone Road

 

Thursday, August 26

            Finish Detweiler Lane/Graystone Road

            Brookfield Lane

            Hogan Lane

            Wolf Lane

            Foxfield Court

 

Friday, August 27

            Ridings Way

 

Monday, August 30

            Ivy Road

            Whitpain Drive

            Meade Road

 

Tuesday, August 31

            Pemberton Road

            Caslon Circle

            Governor’s Way

            Start Bradford Circle

 

Wednesday, September 1

            Finish Bradford Circle

            Narcissa Road

 

Thursday, September 2

            Creek View Lane

            Lafayette Way


As with any paving operation, this work is very weather dependent and some streets on this year's schedule may not be resurfaced until 2022 if Mother Nature does not cooperate.

 Please use caution when driving in work zones and observe all flaggers and signs. 