Posted on: August 15, 2019

Road Resurfacing Continues With Changes For Weather

Rainy weather has caused a brief delay in the Township’s annual road resurfacing project as crews were forced to cancel work on August 13 and 14.

If the weather remains clear, crews will work on Butternut Circle, as well as, Sycamore Place and Hemlock Drive today.

The remaining schedule is:

8/16 Finish Hemlock Dr., Juniper Dr., Hickory Dr.

8/19 Boehms Church Rd., Cross Ln.

8/20 White Oak Rd., Pheasant Meadow Rd., Ginkgo Dr., Beechnut Dr.

8/21 Kurt Dr., Green Tree Rd., Second Ave.

8/22 Clearview Ave., Winchester Dr. Entrance, Talbot Rd.

8/23 Arlington Rd., Vernon Rd, Chalk Ave.

As with any paving operation the work is very weather dependent, and the schedule is subject to change.

Please use caution when driving in work zones and observe all flaggers and signs.